Certified Associate in Project Management (CAPM) — Question 261

A company is executing a critical project with many particular interests and impacts on quality. Which project artifact can be used to document who can influence the use of one kind of resource over another?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Resource management plan, as it specifically outlines how resources are allocated and managed, including who has influence over their use. The other options, such as the Project schedule and Risk register, focus on timelines and potential risks rather than resource allocation. The Stakeholder register identifies stakeholders but does not detail their influence over resource decisions.