Certified Associate in Project Management (CAPM) — Question 241
Which unit of measurement should be used for a project team that wants to optimize changing priorities?
Answer options
- A. Hours
- B. Features
- C. Packages
- D. Points
Correct answer: D
Explanation
Points are often used in agile methodologies to estimate the effort required for tasks and adapt to changing priorities effectively. Hours can be too rigid and may not reflect the complexity of work, while features and packages do not directly address the measurement of effort in a dynamic environment.