Certified Associate in Project Management (CAPM) — Question 233
Which of the following projects is a quality candidate for adaptive approaches?
Answer options
- A. Installing new computers across offices
- B. Designing a new suspension bridge
- C. Upgrading an information system
- D. Retrofitting an old building
Correct answer: C
Explanation
Upgrading an information system often involves evolving requirements and the need for iterative development, making it well-suited for adaptive approaches. In contrast, projects like designing a bridge or retrofitting a building typically have more rigid requirements and fixed processes, while installing new computers is usually a straightforward task with clear specifications.