Certified Associate in Project Management (CAPM) — Question 233

Which of the following projects is a quality candidate for adaptive approaches?

Answer options

Correct answer: C

Explanation

Upgrading an information system often involves evolving requirements and the need for iterative development, making it well-suited for adaptive approaches. In contrast, projects like designing a bridge or retrofitting a building typically have more rigid requirements and fixed processes, while installing new computers is usually a straightforward task with clear specifications.