Certified Associate in Project Management (CAPM) — Question 232

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Answer options

Correct answer: D

Explanation

The correct answer is D, as average velocity and cycle time provide valuable insights into the team's performance and the time required to complete remaining tasks. Options A, B, and C do not directly measure the team's output and efficiency in the context of predicting project duration.