Certified Associate in Project Management (CAPM) — Question 226
Which three processes are generally included in risk management? (Choose three.)
Answer options
- A. Identify Risks
- B. Monitor Risk Costs
- C. Perform Qualitative Risk Analysis
- D. Plan Risk Responses
- E. Estimate Risk Activity Resources
Correct answer: A, C, D
Explanation
The correct processes for risk management are Identify Risks, Perform Qualitative Risk Analysis, and Plan Risk Responses, as they focus on recognizing potential risks, analyzing their impact qualitatively, and developing strategies to address them. Monitor Risk Costs and Estimate Risk Activity Resources, while important, are not core processes of risk management.