Certified Associate in Project Management (CAPM) — Question 199
If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?
Answer options
- A. −8
- B. 1.4
- C. 425
- D. 8
Correct answer: A
Explanation
The variance at completion (VAC) is calculated as VAC = BAC - EAC. In this case, VAC = 17 - 25, which equals −8, making option A correct. The other options are incorrect as they do not reflect the proper calculation of the variance at completion.