If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Answer options

Correct answer: A

Explanation

The variance at completion (VAC) is calculated as VAC = BAC - EAC. In this case, VAC = 17 - 25, which equals −8, making option A correct. The other options are incorrect as they do not reflect the proper calculation of the variance at completion.