Certified Associate in Project Management (CAPM) — Question 198
A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?
Answer options
- A. High-level requirements and the project team
- B. Key stakeholder list and contingency reserve
- C. Detailed milestone schedule and project objectives
- D. Project purpose and high-level project description
Correct answer: D
Explanation
The correct answer is D because a project charter needs to clearly articulate the project's purpose and provide a high-level overview to ensure alignment with strategic objectives. Options A, B, and C focus on specifics that, while important, do not directly establish the connection to the organization's broader goals.