Certified Associate in Project Management (CAPM) — Question 185
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
Answer options
- A. Deliver the product.
- B. Set up a go/no-go meeting.
- C. Set up a meeting with the sponsor.
- D. Wait for the next sprint.
Correct answer: A
Explanation