Certified Associate in Project Management (CAPM) — Question 182
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?
Answer options
- A. Adaptive project management; project schedule and project backlog
- B. Linear project management; project schedule and project backlog
- C. Linear project management; project schedule and work breakdown structure (WBS)
- D. Adaptive project management; project schedule and work breakdown structure
Correct answer: C
Explanation
The correct answer is C because linear project management is suitable for well-defined projects like building a classroom, and a work breakdown structure (WBS) helps in organizing tasks effectively. Options A and D suggest adaptive project management, which is less appropriate for this type of project, and option B lacks the WBS, which is crucial for detailed planning.