Certified Associate in Project Management (CAPM) — Question 181
On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.
What is the advantage of using this tool?
Answer options
- A. Scope creep will be prevented.
- B. Resource allocation will be kept to a minimum.
- C. Project costs will be controlled.
- D. Project closure will be established.
Correct answer: A
Explanation
The correct answer is A because a requirements traceability matrix helps ensure that all requirements are met throughout the project, thus preventing scope creep. Options B, C, and D do not directly relate to the primary purpose of a requirements traceability matrix, which is to maintain project scope rather than manage resources, costs, or closure.