Certified Associate in Project Management (CAPM) — Question 17
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
Answer options
- A. Brainstorming. Monte Carlo simulation, analogous estimation
- B. Three-point estimation, resources leveling, iteration burndown chart
- C. Milestone charts, parametric estimation, schedule baseline
- D. Parametric estimation, three-point estimation, meetings
Correct answer: D
Explanation
The correct answer, D, includes both parametric estimation and three-point estimation, which are widely recognized techniques for accurately estimating activity durations. Options A, B, and C contain methods that are not primarily focused on estimating durations, making them less suitable for this purpose.