What does earned value (EV) measure?
Answer options
- A. Budgeted work that has been completed
- B. Total costs incurred while accomplishing work
- C. Budget associated with planned work
- D. Cost efficiency of budgeted resources
Correct answer: A
Explanation
The correct answer is A because earned value (EV) specifically quantifies the value of work that has been completed against the planned budget. Options B and D focus on costs and efficiency, while option C relates to the budget but does not reflect completed work.