Certified Associate in Project Management (CAPM) — Question 167
Which method should be used to elicit a cross-functional requirement?
Answer options
- A. Focus groups
- B. Prototyping
- C. Interviews
- D. Facilitated workshops
Correct answer: D
Explanation
Facilitated workshops are effective for eliciting cross-functional requirements as they bring together stakeholders from various departments to collaborate and discuss their needs. Focus groups, prototyping, and interviews, while useful in different contexts, may not provide the same level of comprehensive input from multiple functions simultaneously.