Certified Associate in Project Management (CAPM) — Question 166

A project manager engages a highly specialized resource who is in a different location and cannot join the regular team meetings. This is leading to delays in productivity.

How can the project manager assist the team to resolve the issue?

Answer options

Correct answer: D

Explanation

The correct answer is D because consulting the communications management plan allows the project manager to consider alternative communication methods, such as virtual meetings, to include the specialized resource. Options A and C involve relocating or replacing the resource, which may not be feasible or necessary. Option B, while proactive, does not utilize the structured approach that the communications management plan offers.