Certified Associate in Project Management (CAPM) — Question 161

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Answer options

Correct answer: B

Explanation

The correct action is to add the stakeholder to the stakeholder register and include the new risk in the risk register, as this ensures all relevant parties and potential issues are formally recognized and managed. Ignoring the risk because the stakeholder was absent initially is unwise, as risks can arise at any stage. Similarly, documenting the risk only in the lessons learned register does not allow for proactive management during the project's execution.