Certified Associate in Project Management (CAPM) — Question 144
A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?
Answer options
- A. Approving the change
- B. Discussing the change
- C. Reviewing the change
- D. Analyzing the change
Correct answer: A
Explanation
The most critical responsibility in the requirements change process is Approving the change, as it finalizes the decision and ensures that the proposed changes are accepted and implemented. Discussing, reviewing, and analyzing the change are important steps but do not carry the same weight of authority and finality that approval does.