Certified Associate in Project Management (CAPM) — Question 142

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

Answer options

Correct answer: C

Explanation

The correct action is to move the incomplete user stories back to the product backlog for reprioritization, as this allows for a reevaluation of their importance and ensures that the team can focus on completing the most valuable work. Advancing them to the next sprint or extending the current sprint would not address the underlying issues, while removing them entirely could lead to important features being overlooked.