Certified Associate in Project Management (CAPM) — Question 140
A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days.
What should the project manager do?
Answer options
- A. Start the project as soon as possible, as time is short.
- B. Add the milestones to the risk register, as time is short.
- C. Add the two milestones to the project plan, as they are mandatory.
- D. Calculate the duration of the two milestones stated in the contract.
Correct answer: C
Explanation
The correct answer is C because the project plan must include all mandatory milestones to ensure compliance with the contract. Options A and B do not address the necessity of incorporating these milestones into the project plan, while D focuses solely on calculating duration rather than planning.