A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project plan must include all mandatory milestones to ensure compliance with the contract. Options A and B do not address the necessity of incorporating these milestones into the project plan, while D focuses solely on calculating duration rather than planning.