Certified Associate in Project Management (CAPM) — Question 139

During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Project management plan, as it outlines the overall strategy and guidelines for executing the project, including potential changes. The other options, while relevant to product management, do not provide the comprehensive guidance needed for managing project changes.