Certified Associate in Project Management (CAPM) — Question 137
During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?
Answer options
- A. Definition of done (DoD)
- B. Burndown chart
- C. Velocity chart
- D. Definition of ready (DoR)
Correct answer: A
Explanation
The correct answer is the Definition of done (DoD) because it outlines the criteria that must be met for a user story to be considered complete. The other options, such as the Burndown chart and Velocity chart, are useful for tracking progress but do not directly address the readiness of a user story for customer use.