Certified Associate in Project Management (CAPM) — Question 136
A new project manager is assigned to a high-visibility project. The project manager starts with the requirements analysis process.
Who should the project manager onboard to assist with the requirements traceability matrix or analysis?
Answer options
- A. Technical consultant
- B. Project sponsor
- C. Business analyst
- D. Systems analyst
Correct answer: C
Explanation
The correct answer is C, as a Business Analyst specializes in gathering and analyzing requirements, making them essential for creating a requirements traceability matrix. While a Technical Consultant, Project Sponsor, and Systems Analyst may provide valuable insights, they do not focus specifically on requirements analysis like a Business Analyst does.