Certified Associate in Project Management (CAPM) — Question 104
Which is the most accurate description of a backlog in agile?
Answer options
- A. The backlog is the sum of all the story point sizes for the features actually completed in each project iteration.
- B. The backlog is the ordered list of all the work and helps the teams see how to deliver the highest value without creating waste.
- C. The backlog is the ordered list of all the completed work and helps the teams see how to deliver value without creating waste.
- D. The backlog is the ordered list of all the work, shows the work completed, and shows the effect of team members multitasking.
Correct answer: B
Explanation
The correct answer, B, accurately describes the backlog as an ordered list that helps teams prioritize work to maximize value while minimizing waste. Option A incorrectly states that the backlog only includes completed work, while C and D also misrepresent the backlog by emphasizing completed tasks rather than the ongoing prioritization of work.