Certified Pega System Architect v23 — Question 4
In a purchase request case type, you have the following requirement: Purchase requests should automatically go to the manager of an employee.
To meet this requirement, you design a case with a ______________.
Answer options
- A. stage to route requests to the manager
- B. process that routes to the manager
- C. step that routes to the manager
- D. change stage step to allow the employee to route to the manager
Correct answer: B
Explanation
The correct answer is B because a process can effectively manage the workflow of routing purchase requests to the appropriate manager. Options A and C suggest stages and steps, which are not as comprehensive as a process for managing the overall routing. Option D incorrectly implies that an employee would have the authority to route requests, which does not align with the requirement.