Oracle Financial Reporting and Analysis Cloud 2017 Implementation Essentials — Question 32
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud.
(Choose three.)
Answer options
- A. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
- B. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
- C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- D. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- E. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
Correct answer: C, D, E
Explanation
The correct statements are C, D, and E because they accurately describe the flow of information from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management. Options A and B are incorrect as they inaccurately suggest that information flows in the opposite direction.