Oracle CPQ Cloud Service 2016 Implementation Specialist — Question 5

The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.

Answer options

Correct answer: C

Explanation

The correct answer is C because it ensures that resource R2 is available for the entire 24 hours by selecting the Available 24 Hours checkbox and allocating 2 units to both Day and Night Shifts, totaling the required 4 units. Options A and D do not correctly allocate the resources for both shifts, while option B does not make use of the full availability of resource R2.