Oracle CPQ Cloud Service 2016 Implementation Specialist — Question 3

You are monitoring the production status on your shop floor. The production operator informs you that a particular resource that was not functioning for the past week is now back in operation.
Which option shows the steps to quickly release the work orders affected by this operation, which were put on hold using the mobile application?

Answer options

Correct answer: D

Explanation

Option D is correct as it outlines the proper steps to release work orders from the Dispatch List, which is essential for managing operations effectively. The other options either refer to incorrect infotiles or lack necessary steps, making them unsuitable for releasing the work orders in question.