Oracle Field Service Cloud Service 2016 Implementation Specialist — Question 37
Your company is implementing Order Management Cloud to manage the sales orders but fulfilment happens through third party logistics (3PL).
What process should be executed to communicate to the 3PL system that the sales orders are ready to pick release and ship?
Answer options
- A. Manage Shipments Interface
- B. Create Shipments
- C. Confirm Shipments
- D. Generate Shipments Request
- E. Send Shipments Advice
Correct answer: D
Explanation
The correct answer is D, as generating a shipments request is the necessary action to inform the 3PL system about the readiness of sales orders for fulfillment. The other options either refer to different processes or do not specifically address the communication needed for the 3PL to take action on the orders.