Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 60

You are the production scheduler at a manufacturing company. The company is not using advanced warehousing.
You have firmed a planned production order from master planning. The order is ready to be processed.
You now need to process the order in production control.
What should you do first?

Answer options

Correct answer: A

Explanation

The correct first step is to start the order, as this initiates the production process. Estimating the order, scheduling it, or reporting it as finished are subsequent steps that cannot be taken until the order has been started.