Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 56

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.

The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.

You need to configure the system to meet the requirements.

Which three options should you configure? Each answer presents a partial solution.

NOTE: Each correct selection is worth one point.

Answer options

Correct answer: A, B, D

Explanation

The correct answers are A, B, and D because configuring a bottleneck resource helps identify the resource with limited capacity, finite capacity ensures that production does not exceed available machine time, and job scheduling allows for the organization of tasks without overlaps. Option C, operations scheduling, does not specifically address the need for concurrent machine usage, while option E, Capable to Promise, relates to order fulfillment rather than production scheduling.