Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 131
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing company produces electronic components and devices.
The company has scheduling issues related to using working time calendars in manufacturing.
You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.
Solution: Enable route groups for a capacity job type.
Does the solution meet the goal?
Answer options
- A. Yes
- B. No
Correct answer: A
Explanation
The solution of enabling route groups for a capacity job type aligns with the goal of ensuring that the working time calendar is effectively used when scheduling manufacturing jobs. By doing so, the company can better manage its production scheduling in accordance with its working time policies. The other option, 'No', indicates a lack of confidence in this solution, but it is indeed the correct approach to address the scheduling issues.