A company uses Dynamics 365 Supply Chain Management.

Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker’s hours must be allocated to each asset.

You need to configure the system for the worker.

Which configuration should you use?

Answer options

Correct answer: C

Explanation

The correct answer is C because creating one work order and splitting hours by work order job allows for efficient tracking and allocation of the worker's time across multiple assets. Options A and B are not suitable since they pertain to expense and item registrations, which do not address the allocation of labor hours. Option D involves setting standards for labor but does not specifically handle the situation of distributing hours among multiple assets.