Microsoft Dynamics 365 Supply Chain Management — Question 71
A company uses Dynamics 365 Supply Chain Management.
Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker’s hours must be allocated to each asset.
You need to configure the system for the worker.
Which configuration should you use?
Answer options
- A. Create a consumption registration for the expenses.
- B. Create a consumption registration for the items.
- C. Create one work order and split hours by work order job.
- D. Configure labor standards.
Correct answer: C
Explanation
The correct answer is C because creating one work order and splitting hours by work order job allows for efficient tracking and allocation of the worker's time across multiple assets. Options A and B are not suitable since they pertain to expense and item registrations, which do not address the allocation of labor hours. Option D involves setting standards for labor but does not specifically handle the situation of distributing hours among multiple assets.