Microsoft Dynamics 365 Supply Chain Management — Question 70

A company uses Dynamics 365 Supply Chain Management.

Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker’s hours must be allocated to each asset.

You need to configure the system for the worker.

Which configuration should you use?

Answer options

Correct answer: B

Explanation

Creating three separate work orders allows for the precise allocation of the worker's hours to each asset, ensuring that the time spent on each tune-up is tracked individually. The other options do not provide the necessary granularity for hour allocation to each asset, making them less suitable for this scenario.