Microsoft Dynamics 365 Supply Chain Management — Question 33

A company uses the nonconformance functionality in Dynamics 365 Supply Chain Management.

When a manufactured part fails a quality test, a quality clerk creates a nonconformance. You determine that additional items are needed to correct the issue.

You must record the additional items for the nonconformance.

What should you do?

Answer options

Correct answer: D

Explanation

The correct answer is D because approving the nonconformance allows you to formally acknowledge the issue and associate additional operations needed to rectify it. Options A and B involve rejecting the nonconformance, which would not permit you to record the necessary corrective actions, while option C does not address the need to add a related operation.