Microsoft Dynamics 365 Supply Chain Management — Question 30
A company uses planning optimization in Dynamics 365 Supply Chain Management.
A new item is set up for production with a bill of materials (BOM) and is included in planning optimization.
You need to identify the planning output for the item.
What are two parts of the output? Each answer represents a partial solution.
NOTE: Each correct selection is worth one point.
Answer options
- A. warning
- B. production order
- C. purchase order
- D. action message
Correct answer: B, D
Explanation
The correct answers are B and D because a production order is generated as part of the planning output for manufacturing items, and action messages provide notifications related to the planning process. The other options, such as warning and purchase order, do not directly represent the output components of planning optimization for production items.