Microsoft Dynamics 365 Field Service — Question 129
You need to make sure that only a specific set of resources are allowed to be scheduled to perform certain work orders.
Which type should you select when you create a resource requirement preference?
Answer options
- A. Must choose from
- B. Preferred
- C. Restricted
- D. Auto-suggested
Correct answer: A
Explanation
The correct answer is 'Must choose from' because it explicitly limits the selection to a specified group of resources. The other options, such as 'Preferred' and 'Auto-suggested', do not enforce strict limitations, allowing for broader selections which do not meet the requirement of exclusivity.