Managing Projects and Portfolios with Microsoft PPM — Question 14
You use Microsoft PPM to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
You need to be able to see all programs and their associated individual projects from within Project Center.
What should you do?
Answer options
- A. Select the Enterprise Project Type Name field as the value for grouping.
- B. Select the Master Program field as the value for filtering.
- C. Select the Subprojects check box.
- D. Select the Project Details view.
Correct answer: C
Explanation
Selecting the Subprojects check box allows you to display all associated projects under the main program in Project Center, which is essential for visibility. The other options either pertain to grouping or filtering that do not provide the comprehensive view of projects needed in this scenario.