Managing Projects and Portfolios with Microsoft PPM — Question 10
You are an administrator for an organization that uses Microsoft PPM. A project manager is building a team for a project.
The project manager reports that a newly hired resource is not visible in Build Team.
You need to ensure that newly added users are available in Build Team.
What should you do?
Answer options
- A. Edit the user account, set Default Booking Type as Committed.
- B. Edit the user account, select the check box Team Assignment Pool.
- C. Edit the user account, select the check box User can be assigned as a resource.
- D. Edit the user account, set the account status to Active.
Correct answer: D
Explanation
The correct answer is D because setting the account status to Active is necessary for the user to appear in Build Team. Options A, B, and C do not directly enable the visibility of the user in Build Team, as they pertain to different aspects of user management rather than the account status.