Which of the following is a valid drawback of independent testing? 1 credit
Answer options
- A. Developer and independent testing will overlap and waste resources.
- B. Developers loose the sense of responsibility and independent testers may become a bottleneck.
- C. Independent testers need extra education and always cost more.
- D. Independent testers will become a bottleneck and introduce problems in incident management.
Correct answer: B
Explanation
Option B is correct because it highlights the risk of developers becoming disengaged from their responsibilities, while independent testers may slow down the process. Option A inaccurately suggests resource overlap is the main issue, while options C and D focus on education costs and incident management issues, which are less relevant to the sense of responsibility among developers.