Certified in Risk and Information Systems Control (CRISC) — Question 1255

A teaming agreement is an example of what type of risk response?

Answer options

Correct answer: D

Explanation

The correct answer is D, Share, because a teaming agreement involves collaboration to distribute risk among the parties involved. Acceptance (A) implies acknowledging the risk without taking action, Mitigation (B) focuses on reducing the impact or likelihood of the risk, and Transfer (C) means shifting the risk to another party, such as through insurance.