Certified in Risk and Information Systems Control (CRISC) — Question 1254

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months.
Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

Answer options

Correct answer: D

Explanation

The correct answer is D because incorporating risk management into every status meeting ensures continuous monitoring and reassessment of risks throughout the project. Option A is incorrect as risk management should not conclude at planning; option B is too infrequent, and option C suggests a monthly schedule, which may not be necessary if risks are reviewed regularly in meetings.