COBIT 2019 Foundation — Question 72

In the implementation model, when is IT governance implementation risk BEST managed?

Answer options

Correct answer: A

Explanation

The best management of IT governance implementation risk occurs throughout the life cycle, as it allows for ongoing assessment and adjustments at various stages. Focusing only on the planning phase or just before operationalization may overlook critical risks that could arise later in the process.