Certified Information Systems Auditor (CISA) — Question 298

Which of the following is the BEST indicator of the effectiveness of an organization's portfolio management program?

Answer options

Correct answer: A

Explanation

The percentage of investments achieving their forecasted value directly reflects how well the portfolio management program is functioning in delivering expected results. Other options, such as maturity levels or personnel experience, are indirect indicators and may not accurately represent the overall effectiveness of the program. Stakeholder perception, while important, is subjective and does not provide concrete data on actual performance.