Certified in the Governance of Enterprise IT (CGEIT) — Question 229
Which of the following activities MUST be completed before developing an IT strategic plan?
Answer options
- A. Review the enterprise business plan.
- B. Align the enterprise vision statement with business processes.
- C. Review the enterprise risk tolerance level.
- D. Develop an enterprise architecture (EA) framework.
Correct answer: A
Explanation
The correct answer is A, as reviewing the enterprise business plan provides necessary context and direction for the IT strategic plan. Options B, C, and D, while important, are not prerequisites for developing the IT strategic plan and can be addressed subsequently.