Certified in the Governance of Enterprise IT (CGEIT) — Question 194
An enterprise's internal audit group has scheduled a control review of a payroll system project but has been told to wait until the system is implemented. Which of the following is the GREATEST risk associated with the delay?
Answer options
- A. Increased cost to mitigate deficiencies
- B. A delay in the development of new key performance indicators (KPIs)
- C. Continued dependency on compliant legacy systems
- D. Lack of adherence to industry best practices
Correct answer: A
Explanation
The correct answer is A because delaying the audit may lead to issues being identified post-implementation, resulting in higher costs to fix deficiencies that could have been addressed earlier. Options B and C, while important, do not pose the same level of financial risk, and D relates to compliance rather than immediate cost implications.