Entry Certificate in Business Analysis (ECBA) — Question 41

What is a risk that business analysts (BAs) look for when managing stakeholder engagement?

Answer options

Correct answer: B

Explanation

The correct answer, B, 'Delayed approvals', is a significant risk as it can hinder project timelines and impact stakeholder satisfaction. While A, C, and D are also important considerations, they do not directly relate to the engagement aspect of stakeholders as much as delayed approvals do.