Entry Certificate in Business Analysis (ECBA) — Question 18

What tool can be used to determine the impact of a changed requirement on other requirements?

Answer options

Correct answer: B

Explanation

The correct answer is B, Traceability, as it allows you to track the relationships and dependencies between requirements. Verification (A) checks if requirements are met but does not assess their interdependencies. Interview (C) and Workshop (D) are methods for gathering information but do not specifically identify the impact of changes on requirements.