Entry Certificate in Business Analysis (ECBA) — Question 158
The requirements life cycle ends when:
Answer options
- A. solution and the requirements that represent it are retired.
- B. all requirements are verified and validated by the stakeholders.
- C. solution is implemented and the project team disbands.
- D. solution is defined and approved by the stakeholders.
Correct answer: A
Explanation
The correct answer is A because the requirements life cycle officially ends when both the solution and the requirements that define it are retired, indicating they are no longer active. The other options describe stages in the process but do not signify the finality of the requirements life cycle.