Certification of Capability in Business Analysis (CCBA) — Question 491
During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project's scope. The business analyst (BA) facilitating the workshop should:
Answer options
- A. note the issue in the Issue Register to be considered by the Project Manager.
- B. ignore the stakeholder's comment and proceed with the agenda.
- C. consider the issue's impact on the project and gain agreement with stakeholders on the next step.
- D. request the stakeholder to explain the issue further so that possible solutions can be discussed.
Correct answer: C
Explanation
The correct answer is C because it allows the BA to assess any potential implications the issue may have on the project and facilitates a collaborative decision on how to address it with stakeholders. Option A does not involve immediate discussion, while B disregards stakeholder input entirely, and D may lead to an unproductive discussion without addressing the project's scope.