Certification of Capability in Business Analysis (CCBA) — Question 465
A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases. Which requirements attribute can the BA include to allocate the requirements to the proper phase?
Answer options
- A. Status
- B. Author
- C. Priority
- D. Source
Correct answer: C
Explanation
The correct answer is C, Priority, as it helps determine the order in which requirements should be addressed during different phases. Status simply indicates the current state of a requirement, Author identifies who created it, and Source indicates where the requirement originated, but none of these attributes assist in phase allocation.