Linda works as a project manager for an IT project. She is getting new developers for completing her project. Which of the following processes is she involved in?
Answer options
- A. Manage Project Team
- B. Develop Project Team
- C. Acquire Project Team
- D. Human Resource Planning
Correct answer: C
Explanation
The correct answer is C, Acquire Project Team, as it involves obtaining the necessary personnel for the project. The other options, such as Manage Project Team and Develop Project Team, pertain to managing and enhancing existing team members rather than acquiring new ones.